Educational & Institutional

Wilmot Union High School - Wilmot, WI

  • Building Area = 312,000 S.F.
  • Construction Cost = $39.0 million
  • Phase 1 - Gym, Auditorium, Cafeteria, etc.
  • Phase 2 - 2-story building constructed over the demolished footprint
  • Construction - steel joists and masonry bearing walls

Burlington High School - Burlington, WI

  • Building Area = 266,500 S.F.
  • Construction Cost = $32.9 million
  • Four-station field house
  • 460-seat auditorium

Fond Du Lac High School - Fond Du Lac, WI

  • Building Area = 390,000 S.F.
  • Construction Cost = $48.8 million
  • Two-story academic wing with steel frame & composite floor system
  • Single story areas with precast concrete panels or masonry bearing walls
  • Roof framing consists of steel joists and deck

Homestead High School Additions - Mequon, WI

  • Building Area of Additions = 191,000 S.F.
  • Construction Cost = $24.0 million
  • Several additions completed over several years

Door County Justice Center - Sturgeon Bay, WI

  • Building Area (including 2007 addition) = 137,128 S.F.
  • Construction Cost (including 2007 addition) = $16.5 million
  • Detention Center - Precast concrete roof & floors
  • Courthouse floor framing - Composite steel beam and deck
  • Courthouse roof framing - steel joist and deck

Brotz Family Science Building - UW Sheboygan, WI

  • Building Area = 18,125 S.F.
  • Construction Cost = $4.5 million
  • Structural steel frame
  • Precast concrete floor
  • Steel joist & deck roof